Tank Lining
Effluent Tank Coating
Project Scope:
- Transport effluent tank to shop in order to install coating in a controlled environment.
- Diamond grind the concrete surface for abrasion.
- Hand trowel the floor and walls of the tank using polyurethane surfacer.
- Apply topcoat to the polyurethane using chemical resistant epoxy coating system.
Project Timeline:
Completed within a 4-day window, including transportation.
PROJECT
DETAILS
LOCATION:
New Hamburg, ON
New Hamburg, ON
SCOPE:
725 sq.ft
725 sq.ft
MARKET SECTOR:
Commercial